Imagine this: your contractor sends you a photo of your new shower pan filled with water. The message says, “Test passed. We’re installing tile tomorrow.”
Good news. But what exactly does that photo confirm?
How long was the water in the pan? Where was the starting water-level mark? Were the surrounding areas and the space below checked? Which connections were submerged, and which were never part of the test?
You don’t need to become a tile installer to ask these questions. You need to understand what evidence of quality you’re getting before important details disappear behind the tile.
A shower flood test is one of the most useful quality-control steps when building a new shower. But its value depends on how it is performed and how accurately the results are interpreted.
1. First, understand where your shower holds water
When we look at a finished shower, we see tile, grout and a drain. But the tile surface itself is not a complete waterproofing system.
Underneath it, there must be an assembly that contains water and directs it toward the drain. Different showers accomplish this in different ways.
In a traditional assembly, the waterproof shower pan liner sits below the mortar bed that supports the tile. Moisture entering that bed needs a path to the drainage openings in the drain assembly, called weep holes. The slope beneath the waterproofing and the ability of those openings to drain are important.
In a bonded waterproofing system, the waterproof layer sits directly beneath the tile-setting mortar and connects to a compatible drain assembly. Water follows a different drainage path.
A practical question for your contractor:
“Can you show me exactly where the waterproofing is in our shower and how water gets from that layer into the drain?”
A useful answer explains your specific shower assembly. The name of a well-known brand is not enough by itself. What matters is which components are being used and how they connect.
2. What a flood test actually checks
During testing, the waste line is blocked with a suitable test plug. The pan is filled to the specified test level and monitored for the required period.
This checks whether the portion of the assembly being tested holds water.
First, the test plug itself needs to be checked for leakage. Otherwise, water escaping past the plug could be mistaken for a waterproofing failure. Schluter specifically describes checking the plug before filling the entire pan.
It helps to separate three questions:
- Does the pan hold water? This is evaluated through a properly performed flood test.
- Will the assembly drain water correctly? This requires evaluating the slopes and drain assembly.
- Are the other parts of the shower protected? Walls, niches, penetrations, transitions and subsequent installation work require their own checks.
These are different evaluations. One does not replace the others.
3. How a pan can pass the test and still have a problem
Consider a hypothetical example.
A traditional shower pan has a waterproof liner beneath the mortar bed. The liner is intact, and its connection to the drain is watertight. Water stays in place during the test.
But the liner was installed on a flat substrate without the required pre-slope underneath it.
That pan can hold water while failing to drain moisture properly from the mortar bed. Schluter describes missing pre-slope as a cause of persistent saturation in that layer, with increased potential for efflorescence, grout discoloration and other problems.
The practical takeaway: watertightness and proper drainage need to be evaluated separately.
That is why “Did the water level hold?” should be followed by another question:
“How did you check the slope and drainage path in our particular system?”
The reverse is also true: an attractive slope on the finished tile does not, by itself, show what happens to water in the concealed layers.
4. “We waited 24 hours”—after what?
During a remodel, two different time periods are easy to confuse:
- How long to wait after installing the waterproofing before it can be tested.
- How long the test itself must run.
For example, Schluter recommends waiting at least 24 hours after installing KERDI under normal curing conditions before water testing. It also describes 24 hours as a typical duration for the test itself. Lower temperatures may require a longer wait before testing.
But those times cannot be applied to every material.
LATICRETE’s requirements vary by product and conditions. For HYDRO BAN Sheet Membrane, the bonding mortar must cure for at least 24 hours at the specified temperature and humidity before testing. Other products have different requirements.
That is why “We always do it this way” is less useful than a specific answer:
“This is the material we used. Installation was completed at this time. According to its instructions, under our site conditions, testing can begin at this time.”
A number on a package without its conditions of use is not the complete answer.
5. What test record is more useful than a photo of water?
Imagine two records.
The first:
“Everything checked. No leaks.”
The second:
“Primary bathroom shower. Waterproofing system and drain identified. Start and finish times recorded, along with initial and final water levels. Photos and observations from accessible adjacent areas included.”
The second record helps you understand what was actually done. You can show it to another contractor, compare it with construction photos or refer to it during future repairs.
We suggest keeping a small documentation package:
- Waterproofing and drain product names. This lets you find the relevant installation instructions.
- An overall photo before tile installation. This shows the extent of the work completed.
- Close-ups of corners, transitions and the drain connection. These preserve information about details that will be concealed.
- Test start and finish times. These establish the actual duration of the test.
- Comparable photos of the water-level reference. These allow a meaningful comparison rather than relying on impressions.
- Findings, repairs and repeat-test results. These show how any concerns were resolved.
This is not about putting your contractor through an exam. It helps both sides understand the condition of the work.
A photo of a filled pan shows a moment in the process. A record of the conditions and results helps you evaluate the test.

6. The water level dropped. Does that mean there is a leak?
It means the cause needs to be investigated. It does not automatically mean the entire shower is defective.
Possible causes include leakage past the test plug, a defect in the tested assembly or evaporation. Water levels need to be compared at the same reference points and under consistent conditions.
LATICRETE’s procedure includes using a nearby control container with water exposed to comparable conditions to help assess evaporation. This is not a universal allowance for dismissing any drop in water level.
Do not add water to restore the original mark. Once water is added, the original comparison is no longer valid. If leakage is observed, the test should be stopped, the water removed in a controlled manner, the cause corrected and the system retested.
Two questions are worth remembering:
“What explains the change in water level?”
“What check confirmed that explanation?”
“Probably evaporation” remains an assumption until it has been checked.
7. Which areas are outside this test?
Water in the pan tests only the portion of the assembly included in the test. It does not test areas above the water level.
That creates an important limitation: a successful pan test does not establish that an upper wall niche, a shower-arm penetration or every wall detail is watertight.
Schluter’s installation guidance treats penetrations and waterproofing of the required surfaces as separate assembly requirements. In a curbless shower, the extent of the waterproofing and water management beyond the pan itself also matter.
Another practical point: the test applies to the assembly as it existed at the time of testing.
If waterproofing is later damaged by a tool or an attachment detail is changed, the earlier “test passed” record does not verify the new condition.
Before tile installation, discuss:
- How the completed waterproofing will be protected during subsequent work.
- Where glass and accessory attachments are planned.
- How necessary penetrations will be constructed and sealed.
- Who will check any areas changed after the test.
8. Curbless showers: what to clarify
A curbless shower may need a temporary dam to hold water during the test. Schluter specifically addresses this requirement.
For a homeowner, the most important question is not how the temporary barrier is made. It is understanding the limits of the test:
“What area is being tested now, and where does the waterproofing extend to protect the room during normal shower use?”
The temporary dam creates the conditions for testing. It does not show where spray and runoff will travel after the dam is removed.
That is why a photo of the filled test area does not replace a discussion of the layout: the entrance, glass, showerheads and transition to the bathroom floor.
9. When to pause before tile installation
Not every question means demolition is necessary. But some concerns are easier to resolve while the assembly is still accessible.
Reasons to pause may include:
- An unexplained change in water level or the appearance of moisture.
- Visible damage to the waterproofing.
- No clear explanation of the waterproof connection to the drain.
- A proposal to cover a questionable area with tile and “silicone it later.”
- Uncertainty about which materials were used or which installation instructions apply to the detail.
Before testing, the manufacturer recommends inspecting the membrane for defects. Repairs require the necessary material curing time and a repeat test.
At the same time, missing photos do not prove defective work. An unusual-looking detail does not always allow a diagnosis from appearance alone.
A productive technical conversation follows this sequence:
What is the concern? Which requirement applies to that location? How can compliance be checked? What needs to be corrected if a deficiency is confirmed?
This keeps the discussion specific and focused on the work.
10. If the shower is already tiled or has started leaking
This article primarily addresses quality control while a new shower is being built.
If the shower is already finished, missing flood-test records do not automatically mean the tile needs to come off. Start by gathering available information: construction photos, product names, assembly details and the history of the problem.
If a leak has appeared, record:
- Where and when moisture shows up.
- Whether it is associated with shower use.
- What changed before it appeared.
- Whether plumbing work or glass installation was recently performed.
These observations help guide diagnosis, but they do not establish the cause by themselves.
Do not fill an already leaking shower with water as a DIY experiment. Doing so can increase the damage. And do not assume that replacing grout is a universal repair for concealed waterproofing problems.
We explain this further in our related article, “Why Regrouting May Not Fix a Leaking Shower”:
https://micatile.info/2026/10/25/why-regrouting-may-not-fix-a-leaking-shower/
A message you can save and send to your contractor
“Before tile installation, I’d like to keep a record of the work that will be concealed. Please send the waterproofing system and drain names, photos of the pan and key connections, and the water-test record showing the start and finish times, results and any findings.
Please also explain how the slopes were checked, which areas are not included in the pan test, and how the waterproofing will be protected during subsequent work. If an inspection is required for this project, please include information about its completion.”
Discuss this documentation early in the project so your contractor can plan the photos and quality-control steps.
What you should understand before the tile goes in
Before tile installation, a homeowner should have a clear understanding of three things:
How the shower is built. What has been checked. What still needs to be checked.
That gives you a practical basis for discussing quality. The price of the tile, a recognized waterproofing brand and a confident “We always do it this way” do not individually answer those questions.
At Mi Tile Installation Experts, we provide tile installation and shower remodeling in the Sacramento area. Through Mi Audit My Remodel, we also help address questions about work already completed or currently underway.
If you want to understand your shower better, send your city, photos and the current stage of the project. Based on the available information, we can discuss what can be assessed now and which questions require an on-site visit.
Mi Tile Installation Experts
https://micatile.info
Text preferred: (916) 995-6050
Technical references
Schluter — Water testing the Schluter Shower System:
https://www.schluter.com/schluter-us/en_US/faq/shower-system-water-test-how-to
Schluter — Essential Water Management in Tiled Showers:
https://www.schluter.com/schluter-us/en_US/article-water-management-tiled-showers
Schluter — Tiled Shower Waterproofing Systems:
https://www.schluter.com/schluter-us/en_US/article-tiled-shower-waterproofing
LATICRETE — Waterproofing FAQs and product-specific waiting periods:
https://www.laticrete.com/support-and-training/downloads-and-faq/faqs/planning-a-job/waterproofing
LATICRETE — Flood Testing Procedures, TDS 169:
https://cdn-global.laticrete.com/-/media/project/laticrete-international/shared/files/support-and-downloads/technical-datasheets/tds169.ashx